Municipal Related NoticesNews

PLANNED TEMPORARY WATER INTERRUPTION – 27 June 2026 – All Areas

UPDATE: 28 June 2026 – 13:00

📍 UPDATE 5: WATER SUPPLY INTERRUPTION – RESTORATION OF SUPPLY IN PROGRESS

💧 Newton Reservoirs Complex Update:

– Network filling has started: One pump is now in operation to fill the reticulation network. The second pump will be engaged once the network has filled.
– Pump priming: Priming took over an hour. This is critical to ensure air is not released into the network, which can cause burst pipes.
– Upgrades Completed: All repairs and refurbishments planned for this weekend have been successfully completed. This includes the installation of three new valves on the 102-megalitre reservoir, valves at the booster pumps, and replacement of pipework downstream of the tower.

We sincerely apologise for the repeated delays in restoring supply. These were caused by unforeseen work, including breaking the concrete floor for the third valve and pipework replacement at the tower.

Thank You: We extend our utmost appreciation to all residents for your cooperation and support in rolling out the Northern Cape’s largest ever investment in its bulk water supply infrastructure.

Kind regards,

Thabo Mothibi
Communications Unit
Sol Plaatje Municipality


UPDATE: 28 June 2026 – 08:00

📍UPDATE 4: WATER SUPPLY INTERRUPTION – RESTORATION OF SUPPLY DELAYED DUE TO UNSCHEDULED SCOPE OF WORK

Newton Reservoirs Complex Update:

● Pumps at Newton Reservoirs are set to be in operation at 10:00 (in the next two hours).

● All three new valves connected to 102megalitres reservoir are now fully installed.

The breaking of the concrete flooring at the third valve resulted in an unscheduled delay. Valve was fully installed at 23:00 last night.

● Tower Pipework Upgrades: Apart from misalignment challenges, the new pipework installation was also delayed by unscheduled scope of work. Concrete flooring was also encountered and had to be broken down.

We wish to extend our sincerest apologies for the delay in the restoration of the water supply, and we plead for your support and understanding in rolling out the Northern Cape’s largest ever investment in its bulk water supply infrastructure.

Kind regards,

Thabo Mothibi
Communications Unit
SOL PLAATJE MUNICIPALITY


UPDATE: 27 June 2026 – 20:15

📍UPDATE 3: WATER SUPPLY INTERRUPTION FOR ENTIRE KIMBERLEY ON SATURDAY, 27 JUNE 2026

● Two 1200 valves are fully installed.

● The third valve should be done by 23h00.

● Work at Newton booster pumps done.

● We have some misalignment on the pipes from the tower, and this will take more time.

All efforts are aimed at ensuring water supply is restored in the morning of Sunday, 28 June 2026.

We thank all residents for the support given.

Kind regards,

Thabo Mothibi
Communications Unit
SOL PLAATJE MUNICIPALITY


UPDATE: 27 June 2026 – 17:00

📍 UPDATE 2: PLANNED WATER SUPPLY INTERRUPTION – TODAY, 06:00 TO 22:00

Progress update from Newton Reservoirs Complex:

* Two of the three 1200mm NB valves are on schedule. Teams are currently tightening bolts and nuts.
* Third valve: Unforeseen conditions were encountered. The concrete floor is being broken to allow for installation. This has negatively affected the initial completion schedule.
– Newton Tower pipework upgrades: Replacement work is still in progress but is slightly delayed.

Today’s operation at Newton Reservoirs forms part of the government’s investment through the Budget Facility for Infrastructure (BFI) into the repair and upgrade of bulk water supply infrastructure. This is aimed at guaranteeing a reliable future water supply.

We apologise for the inconvenience caused and appreciate residents’ support.

Kind regards,

Thabo Mothibi
Communications Unit
Sol Plaatje Municipality


UPDATE: 27 June 2026 – 10:15

📍UPDATE 1: PLANNED WATER SUPPLY INTERRUPTION OF TODAY – 06:00 TO 22:00

* With the pipeline emptied on time, the operation at Newton Reservoirs commenced on schedule at 06:00, with all the teams getting down to their assigned tasks.

• Two of the three (3) 1200 old valves have been cut off for installation of new ones at reservoir 102megalitres.

* The scope for today also includes pipework upgrades at the tower of the Newton Reservoirs Complex, and replacement work is in progress.

Today’s operation at Newton Reservoirs is part of the government’s investment through the Budget Facility for Infrastructure (BFI) into the repairs and upgrades of the bulk water supply infrastructure This is aimed at guaranteeing reliable future water supply.

We apologise for the inconvenience caused and appreciate the residents’ support.

Kind regards,

Thabo Mothibi
Communications Unit
SOL PLAATJE MUNICIPALITY


UPDATE: 24 June 2026 – 07:00

⚠️ ALERT 1: WATER SUPPLY INTERRUPTION FOR ENTIRE KIMBERLEY ON SATURDAY, 27 JUNE 2026 – 06:00 TO 22:00

Notice is hereby given that a Planned Water Supply Interruption is scheduled for refurbishments at Newton Reservoirs:

• Installation of three new valves (1200 NB) at Reservoir 102 megalitres at Newton Reservoirs, and
• Newton Tower pipework upgrades (tower to cross section).

Interruption schedule:

* Date: Saturday, 27 June 2026
* Time: 06:00 to 22:00 (16 hours)

📍Please Store Water: Residents are urged to store sufficient water for essential use during the time of interruption.

Saturday’s operation at Newton Reservoirs is part of the government’s investment through the Budget Facility for Infrastructure (BFI) into repairs and upgrades of the bulk water supply infrastructure. This is aimed at guaranteeing reliable future water supply.

We apologise for any inconvenience caused and would appreciate the residents’ cooperation.

Kind regards,

Thabo Mothibi
Communications Unit